Cerro Matoso is a mine in Colombia on record for nickel.

45.5 kt

Latest recorded output: Nickel, contained in mine output, 2019

STALE 2022

  • Type and status

    Mine

    Status not recorded in the source.

  • Latest recorded production

    45.5 kt

    Nickel, contained in mine output, 2019

  • Water stress of the sub-basin

    Low (<10%)

    Modelled baseline of the place, 2023

Overview

Map

Basemap: Natural Earth (public domain)
  • Cerro Matoso: Mine
  • Colombia

The ring marks the coordinates the source gives.

Key facts

Type
Mine (listed as: Mine, Smelter)
Location (lat, lon)
7.9225, -75.5479
Commodities and products, as listed
Nickel
Status, as listed
Not recorded in the source
Owner, as listed
South32 (99.9%) (as of 2019)

Another source describes the same site. The atlas draws that record on the map: Cerro Matoso Mine (USGS OFR 2017-1079 (Latin America and the Caribbean))

Supply chain

Where this site sits in the chain: what the record lists, and what else is on record nearby.

Materials on record

Kind of site
Mine
Commodities and products, as listed
Nickel

In Colombia

The atlas has 3 sites on record in Colombia.

Country profile: ColombiaCompare with another site

Sites come from a USGS compilation for Latin America and the Caribbean that describes 2014, the national surveys of Australia (plants, mines, critical-mineral deposits), Canada (mines, smelters, refineries, critical-mineral projects) and Sweden (mines in operation and significant prospects), a 2022 database of coal and metal mines, and mine areas mapped by OpenStreetMap volunteers (marked as estimated). A deposit or a project is not a mine and is never counted as one. Processing plants in Asia, Africa and Europe are mostly missing. A missing facility means it is not in these sources, not that it does not exist.

Money

Capacity and yearly production as the sources record them. The atlas has no revenue, cost or value figure for a single site.

Production by year

Tonnes, as the database took them from company and agency reports. Years without a reported figure are left out, not filled in.

Nickel · contained in mine output 2001–2019, 19 years
YearTonnesSource
201945 496Reporting period: July-June

South32 Limited (2019) Quarterly Report June 2019 ; Estimate (value) ; Estimate (grade) ↗

201848 773Reporting period: July-June

South32 Limited (2019) Quarterly Report June 2019 ; Estimate (value) ; Estimate (grade) ↗

201736 537Reporting period: July-June

South32 Limited (2017) Quarterly Report June 2017 ; Estimate (value) ↗

201636 837Reporting period: July-June

South32 Limited (2017) Quarterly Report June 2017 ; Estimate (value) ↗

201540 440Reporting period: July-June

South32 Limited (2015) Quarterly Report June 2015 ; Estimate (value) ↗

201444 344Reporting period: July-June

South32 Limited (2015) Quarterly Report June 2015 ; Estimate (value) ↗

201350 851Reporting period: July-June

BHP Billiton (2013) Production Report for the year ended 30 June 2013 ↗

201248 949Reporting period: July-June

BHP Billiton (2013) Production Report for the year ended 30 June 2013 ↗

201140 040Reporting period: July-June

BHP Billiton (2011) Production Report for the year ended 30 June 2011 ↗

201049 650Reporting period: July-June

BHP Billiton (2011) Production Report for the year ended 30 June 2011 ↗

200950 551Reporting period: July-June

BHP Billiton (2009) Quarterly Production Report - June 2009 ↗

200841 842Reporting period: July-June

BHP Billiton (2009) Quarterly Production Report - June 2009 ↗

200751 051Reporting period: July-June

BHP Billiton (2007) Quarterly Production Report - June 2007 ↗

200651 552Reporting period: July-June

BHP Billiton (2007) Quarterly Production Report - June 2007 ↗

200551 351Reporting period: July-June

BHP Billiton (2005) Quarterly Production Report - June 2005 ↗

200449 149Reporting period: July-June

BHP Billiton (2005) Quarterly Production Report - June 2005 ↗

200346 947Reporting period: July-June

BHP Billiton (2003) Quarterly Production Report - June 2003 ↗

200240 440Reporting period: July-June

BHP Billiton (2003) Quarterly Production Report - June 2003 ↗

200131 832Reporting period: July-June

BHP Billiton (2001) Quarterly Production Report - June 2001 ↗

These figures are informational, not financial advice.

Sustainability

Four indicators, the same on every profile. For a single site most of them are properties of the place or the country, and are labelled so.

  • Carbon

    Emissions intensity of the electricity grid of Colombia: the country's grid, not this site's.

    186gCO2e/kWh

    2025Reported

    Higher than 25% of the other 208 countries with a grid figure.

    • The atlas has no record of this site's own power supply or emissions.
  • Water

    Baseline water stress of the sub-basin the site lies in.

    Low (<10%)

    2023Estimated

    This is a class, not a figure, so no percentile is given.

    • 2.2% of the available supply is withdrawn in the sub-basin.
    • A modelled property of the place, not a measure of the site's own water use.
    • "Arid and Low Water Use" is a class of its own in the source and is not counted as high.
  • Land

    Land visibly used by mining.

    Not available per site: the atlas holds the mapped area per country only.

    • Mapped from satellite images for all mining in a country. It cannot be attributed to one material or one site.
  • Circularity

    Recycling's share of demand.

    Not available per site: the atlas has no recycling figure for single sites.

There is no overall score: the four figures measure different things and are not added up. How to read these figures

Risks & policy

Export controls in force

Compiled by USGS, effective January 2026. Not a live feed.

USGS Table 4 lists no export control by Colombia for the materials of this site.

Chokepoints at sea

The atlas has no record of which minerals pass through which sea passage, so no chokepoint figure is attached to this profile. Current ship counts for the main passages are on the Live page. Open the Live page

What the atlas does not know about sites

Sites come from a USGS compilation for Latin America and the Caribbean that describes 2014, the national surveys of Australia (plants, mines, critical-mineral deposits), Canada (mines, smelters, refineries, critical-mineral projects) and Sweden (mines in operation and significant prospects), a 2022 database of coal and metal mines, and mine areas mapped by OpenStreetMap volunteers (marked as estimated). A deposit or a project is not a mine and is never counted as one. Processing plants in Asia, Africa and Europe are mostly missing. A missing facility means it is not in these sources, not that it does not exist.

Add data

Sources

Every source this profile uses, with its licence, the years its figures describe and how sure the figures are. Each chip on the profile opens the single record.

{n} record used

This record comes from

The database took it from: BHP Billiton (2013) Annual Report 2013 ↗

History & talk

Revision history and discussion are coming soon.

Every change to a figure will be listed here with its source, its credit and its review, and each profile will have a place to discuss it. Until then the data changes only when a source is updated, and every figure links to that source.

What can be contributed today

What we don't know yet

No open source we may use gives these figures. Nothing is estimated to fill them. If you know a public source, add it.

Type the name of a material, a country, a site or a company.