# Investment pipeline: planned and under-construction projects with a publicly announced capital cost, # public financial backing, or both. Hand-read on 2026-11-13; a short list, not a census. # # Every fact is one statement on one page: url, date, publisher and the publisher's own words (quote, at most # 30 words). The pages were saved as text when read; pipeline/extracts/announcements/SOURCE.json holds their # checksums, and wherever the texts are on disk the build checks every quote word for word. An amount must be # printed in its quote unless `amount_check` says why not. Nothing here is typed from memory. # # - `status` is ours (planned | construction); `status_fact.as_printed` is the publisher's wording on that date. # - `stage_as_printed` says how firm a backing is. A letter of interest or a conditional commitment is not a loan. # - Amounts stay in the currency of the statement and are never converted or added up. # - eib.org is link-only (its terms of use forbid republication): no figure is taken from it. Where a project has # an EIB page, `links` holds its address and nothing else. No openly reusable source for those figures was found. # # Read and left out: # keliber-lithium: construction was completed in April 2026 (Finnish Minerals Group), so it is no longer planned or under construction # skouries: first concentrate was produced in September 2026; the status page is undated # pirdop-tankhouse-expansion: its status and loan were read on eib.org only, which is link-only # metlen-gallium-bauxite: its status, cost and loan were read on eib.org only, which is link-only # vulcan-lionheart: backing by European Investment Bank (read on a link-only site) # vulcan-lionheart: backing by German government (read on a link-only site) # vulcan-lionheart: announced capital cost (read on a link-only site) # talga-vittangi-anode: backing by European Investment Bank (read on a link-only site) # Westwater Resources, graphite, Alabama: company site answered 403 for the release needed for capex and status; only the EXIM statement was read # Serra Verde, Pela Ema rare earths mine, Brazil: source describes optimizing and expanding an existing mine; no capex and no planned/construction status read # Cove Kaz Capital, Severniy Katpar Tungsten Mine, Kazakhstan: letters of interest only; no project status and no capex read # Seven Australian projects (rare earths, graphite and others): EXIM gives only a combined total, no per-project amount # Zinnwald Lithium, Jadar, Viscaria, Talon Metals, Arafura Nolans: no capital cost or current standing read on a primary page projects: - id: thacker-pass name: Thacker Pass company: Lithium Americas Corp. country_iso3: USA place: Humboldt County, Nevada materials: - lithium kind: mine_and_processing kind_as_printed: Thacker Pass lithium project status: construction status_fact: as_printed: major construction of the processing plant at Thacker Pass Phase 1 date: "2026-05-14" url: https://lithiumamericas.com/news/news-details/2026/Lithium-Americas-Reports-First-Quarter-2026-Results/default.aspx quote: The Company continues to progress major construction of the processing plant at Thacker Pass Phase 1, targeting mechanical completion in late 2027. source_file: lac-q1-2026-results.txt publisher: Lithium Americas Corp. capex: amount: 2930000000 currency: USD what_it_covers: total Capex estimate per the Company's Technical Report (effective December 31, 2024), Thacker Pass Phase 1; source says it did not include any exposure to tariffs date: "2026-05-14" url: https://lithiumamericas.com/news/news-details/2026/Lithium-Americas-Reports-First-Quarter-2026-Results/default.aspx quote: of which $1.1 billion is part of the total Capex estimate of $2.93 billion per the Company’s Technical Report. source_file: lac-q1-2026-results.txt publisher: Lithium Americas Corp. backing: - body: U.S. Department of Energy, Loan Programs Office instrument: loan stage_as_printed: closed amount: 2260000000 currency: USD date: "2025-03-28" url: https://lithiumamericas.com/news/news-details/2025/Lithium-Americas-Reports-2024-Full-Year-Results/default.aspx quote: Loan Programs Office closed a $2.26 billion loan under the Advanced Technology Vehicles Manufacturing Loan Program source_file: lac-2024-full-year-results.txt publisher: Lithium Americas Corp. note: the statement dates the event itself to 2024-10-28 - body: U.S. Department of Energy, Loan Programs Office instrument: equity stage_as_printed: restructured its deal; 5% equity ownership in the form of LAC warrants date: "2025-09-30" url: https://www.energy.gov/articles/department-energy-restructures-lithium-americas-deal-protect-taxpayers-and-onshore quote: The new terms provide the U.S. Government with 5% equity ownership in the form of LAC warrants source_file: doe-lithium-americas-restructure-2025.txt publisher: U.S. Department of Energy - body: U.S. Department of Energy instrument: loan stage_as_printed: Project financing for Phase 1 includes a $2.23 billion loan amount: 2230000000 currency: USD date: "2026-05-14" url: https://lithiumamericas.com/news/news-details/2026/Lithium-Americas-Reports-First-Quarter-2026-Results/default.aspx quote: Project financing for Phase 1 includes a $2.23 billion loan from the U.S. DOE and strategic investments from GM and Orion. source_file: lac-q1-2026-results.txt publisher: Lithium Americas Corp. - id: rhyolite-ridge name: Rhyolite Ridge Lithium-Boron Project company: Ioneer country_iso3: USA place: Nevada materials: - lithium kind: mine_and_processing kind_as_printed: Rhyolite Ridge Lithium-Boron Project status: planned status_fact: as_printed: the Board will be positioned to consider a Final Investment Decision (FID) date: 2026-08 url: https://www.ioneer.com/wp-content/uploads/2026/08/Rhyolite-Ridge-Quarterly-Newsletter-August-2026.pdf quote: the Board will be positioned to consider a Final Investment Decision (FID) and move into early construction work source_file: ioneer-newsletter-2026-08.txt publisher: Ioneer note: newsletter prints only AUGUST 2026 capex: amount: 1683000000 currency: USD what_it_covers: "AACE Class 2 capital cost estimate (-10%, +15%) including a 10% contingency; table row: Initial capital expenditure (including contingencies) US$M 1,683.2" date: "2025-10-29" url: https://www.ioneer.com/investors/dfs-summary-2025-update/ quote: U.S.$1,683 million – AACE Class 2 capital cost estimate (-10%, +15%) including a 10% contingency source_file: ioneer-dfs-summary-2025.txt publisher: Ioneer note: web page is undated; it says the metrics were originally published in Ioneer's announcement on October 29, 2025 backing: - body: U.S. Department of Energy, Office of Energy Dominance Financing (formerly Loan Programs Office) instrument: loan stage_as_printed: closed amount: 996000000 currency: USD date: "2025-12-19" url: https://www.ioneer.com/wp-content/uploads/2025/12/Ioneer_Year_End_2025_Release_FINAL.pdf quote: In January, Rhyolite Ridge closed a US$996 million loan with the U.S. Department of Energy source_file: ioneer-year-end-2025.txt publisher: Ioneer note: the statement dates the event itself to 2025-01 - body: U.S. Department of Energy, Office of Energy Dominance Financing (formerly Loan Programs Office) instrument: loan stage_as_printed: has conditions to first draw date: "2025-12-19" url: https://www.ioneer.com/wp-content/uploads/2025/12/Ioneer_Year_End_2025_Release_FINAL.pdf quote: $968 million in principal and $28 million in capitalised interest and has conditions to first draw source_file: ioneer-year-end-2025.txt publisher: Ioneer - id: south-west-arkansas name: South West Arkansas Project company: Smackover Lithium country_iso3: USA place: southern Arkansas materials: - lithium kind: mine_and_processing kind_as_printed: Direct Lithium Extraction status: planned status_fact: as_printed: expects to take FID by the end of the first quarter of 2027 date: "2026-11-13" url: https://www.standardlithium.com/projects/smackover/south-west-arkansas/ quote: Smackover Lithium expects to take FID by the end of the first quarter of 2027, with construction beginning shortly thereafter source_file: sli-swa-project.txt publisher: Standard Lithium Ltd. note: project web page is undated; date is the fetch date capex: amount: 1450000000 currency: USD what_it_covers: All-in Class III capex estimate (Definitive Feasibility Study), includes a 12.3% contingency date: "2026-11-13" url: https://www.standardlithium.com/projects/smackover/south-west-arkansas/ quote: All-in Class III capex estimate of $1.45 billion includes a 12.3% Monte Carlo risked contingency. source_file: sli-swa-project.txt publisher: Standard Lithium Ltd. note: project web page is undated; date is the fetch date; page refers to a DFS press release dated September 3, 2025 backing: - body: U.S. Department of Energy, Office of Manufacturing & Energy Supply Chains instrument: grant stage_as_printed: closed amount: 225000000 currency: USD date: "2025-01-16" url: https://www.standardlithium.com/news/standard-lithium-and-equinor-finalize-225-million-grant-from-the-us-department-of-energy-for-the-south-west-arkansas-project quote: has closed the US$225 million grant from the U.S. Department of Energy’s source_file: sli-doe-grant-final.txt publisher: Standard Lithium Ltd. - id: stibnite-gold-project name: Stibnite Gold Project company: Perpetua Resources Corp. country_iso3: USA place: Valley County, Idaho materials: - antimony kind: mine_and_processing kind_as_printed: Stibnite Gold Project status: construction status_fact: as_printed: early works construction; Final Investment Decision expected in the second half of 2026 date: "2026-05-11" url: https://perpetuaresources.com/wp-content/uploads/Perpetua-Resources-Q1-2026-PR.pdf quote: continued early works construction and began procurement for long-lead time items ahead of our Final Investment Decision expected in the second half of 2026 source_file: perpetua-q1-2026.txt publisher: Perpetua Resources Corp. capex: amount: 2576000000 currency: USD what_it_covers: Initial Capital, including contingency; exclusive of pre-production revenue (Technical Report Summary as of December 31, 2025) date: "2026-03-31" url: https://perpetuaresources.com/wp-content/uploads/U.S.-EXIMs-Board-Advances-Proposed-2.7-Billion-Loan-to-Congressional-Notice-Perpetua-Announces-Improved-Project-Economics_March-31-2026.pdf quote: Initial Capital, reflects estimated total capital expenditures of $2,576 million as of December 31, 2025, including a contingency of $191.9 million source_file: perpetua-exim-2026-03-31.txt publisher: Perpetua Resources Corp. backing: - body: Export-Import Bank of the United States instrument: loan stage_as_printed: unanimously agreed to notify Congress of a proposed amount: 2700000000 currency: USD date: "2026-03-31" url: https://perpetuaresources.com/wp-content/uploads/U.S.-EXIMs-Board-Advances-Proposed-2.7-Billion-Loan-to-Congressional-Notice-Perpetua-Announces-Improved-Project-Economics_March-31-2026.pdf quote: unanimously agreed to notify Congress of a proposed $2.7 billion senior secured long-term loan source_file: perpetua-exim-2026-03-31.txt publisher: Perpetua Resources Corp. - body: Export-Import Bank of the United States instrument: loan stage_as_printed: unanimously approved amount: 2900000000 currency: USD date: "2026-05-21" url: https://perpetuaresources.com/wp-content/uploads/Perpetua-Resources-EXIM-press-release-May-21-2026-FINAL.pdf quote: has unanimously approved a $2.9 billion senior secured long-term loan source_file: perpetua-exim-2026-05-21.txt publisher: Perpetua Resources Corp. - id: graphite-creek name: Graphite Creek Project company: Graphite One Inc. country_iso3: USA place: north of Nome, Alaska materials: - graphite kind: mine kind_as_printed: Graphite Creek mine development status: planned status_fact: as_printed: Management’s current plan is for graphite to be mined date: "2025-11-13" url: https://www.graphiteoneinc.com/wp-content/uploads/2026/01/Q3-2025-MDA-Final-1.pdf quote: Management’s current plan is for graphite to be mined from the Company’s Graphite Creek Property source_file: graphiteone-q3-2025-mda.txt publisher: Graphite One Inc. backing: - body: Export-Import Bank of the United States instrument: letter_of_interest stage_as_printed: Letter of Interest amount: 670000000 currency: USD date: "2026-01-05" url: https://www.exim.gov/news/exim-delivers-for-america-2025 quote: approving a $670 million Letter of Interest for Graphite One Inc. (G1) to support financing of the Company's Graphite Creek Project source_file: exim-delivers-2025.txt publisher: Export-Import Bank of the United States note: the statement dates the event itself to 2025-12-18 - body: Export-Import Bank of the United States instrument: letter_of_interest stage_as_printed: non-binding and conditional and does not represent a financing commitment date: "2025-12-18" url: https://www.graphiteoneinc.com/exim-bank-increases-letters-of-interest-for-the-graphite-one-supply-chain-to-2-07-billion/ quote: Investors should be aware that the LoI is non-binding and conditional and does not represent a financing commitment. source_file: graphiteone-exim-2-07b.txt publisher: Graphite One Inc. - body: U.S. Department of Defense (Defense Production Act) instrument: grant stage_as_printed: drew down the remaining amount: 37500000 currency: USD date: "2025-11-13" url: https://www.graphiteoneinc.com/wp-content/uploads/2026/01/Q3-2025-MDA-Final-1.pdf quote: the U.S. Department of Defense’s $37.5 million Technology Investment Agreement grant under the Defense Production Act source_file: graphiteone-q3-2025-mda.txt publisher: Graphite One Inc. - id: elk-creek name: Elk Creek Project company: NioCorp Developments Ltd. country_iso3: USA place: southeast Nebraska materials: - rare-earths kind: mine_and_processing kind_as_printed: Processing Plant and Mining Operation Producing Eight Critical Minerals status: planned status_fact: as_printed: subject to satisfactory completion of EXIM’s current due diligence review of NioCorp’s application for debt financing date: "2026-10-15" url: https://www.niocorp.com/exim-reiterates-target-to-finance-approximately-65-of-elk-creek-project-upfront-capex/ quote: subject to satisfactory completion of EXIM’s current due diligence review of NioCorp’s application for debt financing source_file: niocorp-exim-65pct.txt publisher: NioCorp Developments Ltd. capex: amount: 1850000000 currency: USD what_it_covers: "Upfront Capital Estimate (2026 Feasibility Study); table row: Total Upfront CAPEX ($M) $1,849" date: "2026-08-10" url: https://www.niocorp.com/niocorp-project-to-expand-production-to-8-made-in-usa-critical-minerals-over-a-40-year-mine-life-with-an-estimated-4-1-billion-pre-tax-npv8%C2%B9/ quote: Upfront Capital Estimate of $1.85 Billion Reflects a Substantially Redesigned Processing Plant and Mining Operation source_file: niocorp-fs-2026.txt publisher: NioCorp Developments Ltd. backing: - body: Export-Import Bank of the United States instrument: other stage_as_printed: letter of support date: "2026-10-15" url: https://www.exim.gov/news/chairman-jovanovic-signs-letter-support-for-niocorps-elk-creek-mine-tours-innovative-project quote: The Export-Import Bank of the United States’ letter of support marks an important step towards making the Elk Creek Critical Minerals Project a reality source_file: exim-niocorp-letter.txt publisher: Export-Import Bank of the United States - body: Export-Import Bank of the United States instrument: other stage_as_printed: target ... of providing debt financing equivalent to approximately 65% of the Project’s upfront CAPEX requirements date: "2026-10-15" url: https://www.niocorp.com/exim-reiterates-target-to-finance-approximately-65-of-elk-creek-project-upfront-capex/ quote: EXIM retains our target outlined in the Preliminary Project Letter of providing debt financing equivalent to approximately 65% of the Project’s upfront CAPEX requirements source_file: niocorp-exim-65pct.txt publisher: NioCorp Developments Ltd. - id: kabanga-nickel name: Kabanga Nickel Project company: Lifezone Metals Limited country_iso3: TZA place: northwestern Tanzania materials: - nickel - copper - cobalt kind: mine kind_as_printed: mechanized underground mine, mill, concentrator status: planned status_fact: as_printed: on track for a Final Investment Decision (FID) in 2026 date: "2025-12-11" url: https://ir.lifezonemetals.com/news/press-releases/news-details/2025/Lifezone-Metals-Advances-Kabanga-Nickel-Project-Toward-2026-Final-Investment-Decision/default.aspx quote: which remains on track for a Final Investment Decision (FID) in 2026 source_file: lifezone-fid-2025.txt publisher: Lifezone Metals Limited capex: amount: 942000000 currency: USD what_it_covers: Pre-production capital costs, including 9.7% contingency (Feasibility Study, initial development phase) date: "2025-07-18" url: https://ir.lifezonemetals.com/news/press-releases/news-details/2025/Lifezone-Metals-Files-the-Feasibility-Study-Technical-Report-Summary-for-the-Kabanga-Nickel-Project-in-Tanzania/default.aspx quote: Pre-production capital costs of $942 million, including 9.7% contingency. source_file: lifezone-fs-2025.txt publisher: Lifezone Metals Limited backing: - body: U.S. International Development Finance Corporation (DFC) instrument: letter_of_interest stage_as_printed: Letter of Interest date: "2024-09-23" url: https://ir.lifezonemetals.com/news/press-releases/news-details/2024/Lifezone-Metals-Announces-Initiation-of-Project-Financing-Process-for-the-Kabanga-Nickel-Project-in-Tanzania/default.aspx quote: has received a Letter of Interest from the U.S. International Development Finance Corporation (DFC) that expressed DFC’s interest in considering the Project for loans source_file: lifezone-dfc-loi-2024.txt publisher: Lifezone Metals Limited - id: us-smelter-clarksville name: U.S. Smelter company: Korea Zinc country_iso3: USA place: Clarksville, Tennessee materials: - copper - antimony - gallium - germanium kind: processing kind_as_printed: large-scale smelter status: planned status_fact: as_printed: Full-scale construction will start in 2027 date: "2025-12-15" url: https://www.koreazinc.co.kr/en/korea-zinc-partners-with-the-u-s-department-of-war-and-u-s-department-of-commerce-to-build-a-state-of-the-art-critical-minerals-smelter-in-the-united-states-with-6-6-billion-of-capital-expenditures/ quote: Full-scale construction will start in 2027, with completion planned for 2029 source_file: koreazinc-us-smelter.txt publisher: Korea Zinc capex: amount: 6600000000 currency: USD what_it_covers: capital expenditures; total planned investment of $7.4 billion including working capital and financing costs date: "2025-12-15" url: https://www.koreazinc.co.kr/en/korea-zinc-partners-with-the-u-s-department-of-war-and-u-s-department-of-commerce-to-build-a-state-of-the-art-critical-minerals-smelter-in-the-united-states-with-6-6-billion-of-capital-expenditures/ quote: is expected to have $6.6 billion in capital expenditures, with a total planned investment of $7.4 billion including working capital and financing costs source_file: koreazinc-us-smelter.txt publisher: Korea Zinc backing: - body: U.S. Department of War instrument: other stage_as_printed: conditional investment amount: 1400000000 currency: USD date: "2025-12-15" url: https://www.koreazinc.co.kr/en/korea-zinc-partners-with-the-u-s-department-of-war-and-u-s-department-of-commerce-to-build-a-state-of-the-art-critical-minerals-smelter-in-the-united-states-with-6-6-billion-of-capital-expenditures/ quote: The Department of War’s conditional investment of $1.4 billion to build the first U.S.-based zinc smelter and critical minerals processing facility source_file: koreazinc-us-smelter.txt publisher: Korea Zinc - body: U.S. Department of War together with investors instrument: other stage_as_printed: arranged by the U.S. Department of War together with investors amount: 2150000000 currency: USD date: "2025-12-15" url: https://www.koreazinc.co.kr/en/korea-zinc-partners-with-the-u-s-department-of-war-and-u-s-department-of-commerce-to-build-a-state-of-the-art-critical-minerals-smelter-in-the-united-states-with-6-6-billion-of-capital-expenditures/ quote: Approximately $2.15 billion, arranged by the U.S. Department of War together with investors, will be invested in the smelter construction. source_file: koreazinc-us-smelter.txt publisher: Korea Zinc - body: U.S. Department of Commerce (CHIPS Act) instrument: grant stage_as_printed: will provide $210 million in award funding amount: 210000000 currency: USD date: "2025-12-15" url: https://www.koreazinc.co.kr/en/korea-zinc-partners-with-the-u-s-department-of-war-and-u-s-department-of-commerce-to-build-a-state-of-the-art-critical-minerals-smelter-in-the-united-states-with-6-6-billion-of-capital-expenditures/ quote: The U.S. Department of Commerce will provide $210 million in award funding under the CHIPS Act for U.S. equipment procurement and other purposes. source_file: koreazinc-us-smelter.txt publisher: Korea Zinc - id: arctic-upper-kobuk name: Arctic Project company: Ambler Metals LLC country_iso3: USA place: northwestern Alaska materials: - copper kind: mine kind_as_printed: open-pit status: planned status_fact: as_printed: targeting a Record of Decision in September 2028 date: "2026-10-02" url: https://trilogymetals.com/news-and-media/news/trilogy-metals-reports-third-quarter-fiscal-2026-financial-results/ quote: The schedule sets an estimated 29-month integrated review timetable targeting a Record of Decision in September 2028 source_file: trilogy-q3-fy2026.txt publisher: Trilogy Metals Inc. capex: amount: 1176800000 currency: USD what_it_covers: Initial capital expenditure (2023 Arctic feasibility study); sustaining capital and closure are separate figures date: "2023-02-14" url: https://trilogymetals.com/news-and-media/news/trilogy-metals-announces-updated-feasibility-study-results-for-the-arctic-project/ quote: Initial capital expenditure is $1,176.8 million and sustaining capital is $114.4 million source_file: trilogy-arctic-fs-2023.txt publisher: Trilogy Metals Inc. backing: - body: U.S. Department of War instrument: equity stage_as_printed: Closing amount: 35600000 currency: USD date: "2026-10-02" url: https://trilogymetals.com/news-and-media/news/trilogy-metals-reports-third-quarter-fiscal-2026-financial-results/ quote: Closing of the DOW $35.6 million strategic equity investment subsequent to quarter end on September 11, 2026. source_file: trilogy-q3-fy2026.txt publisher: Trilogy Metals Inc. note: the statement dates the event itself to 2026-09-11 - id: mactung name: Mactung company: Fireweed Metals Corp. country_iso3: CAN place: Macmillan Pass, Yukon Territory materials: - tungsten kind: mine kind_as_printed: Mactung tungsten project status: planned status_fact: as_printed: commencing a Feasibility Study date: "2025-11-24" url: https://fireweedmetals.com/mactung-project-update/ quote: Fireweed anticipates that the Feasibility Study will run throughout 2026 and is targeting a 2027 release. source_file: fireweed-mactung-update.txt publisher: Fireweed Metals Corp. backing: - body: U.S. Department of Defense (Defense Production Act Title III) instrument: grant stage_as_printed: awarded amount: 15800000 currency: USD date: "2024-12-13" url: https://fireweedmetals.com/fireweed-metals-corp-awarded-up-to-c35-4-m-in-joint-us-canadian-government-funding-to-advance-mactung-and-essential-infrastructure-to-unlock-the-critical-minerals-district-at-macmillan-pass-yukon-t/ quote: Fireweed has been awarded US$15.8M (~C$22.5 M) from the U.S. Department of Defense under Title III of the Defense Production Act of 1950 source_file: fireweed-dpa-award.txt publisher: Fireweed Metals Corp. - id: electra-cobalt-refinery name: cobalt sulfate refinery company: Electra Battery Materials Corporation country_iso3: CAN place: Temiskaming Shores materials: - cobalt kind: processing kind_as_printed: cobalt sulfate refinery status: planned status_fact: as_printed: early works program ... to prepare for the restart of full-scale construction date: "2025-06-19" url: https://electrabmc.com/news-releases/news/electra-commences-early-works-to-support-restart-of-north-americas-only-cobalt-refinery quote: The early works program encompasses targeted site-level activities designed to prepare for the restart of full-scale construction. source_file: electra-early-works.txt publisher: Electra Battery Materials Corporation capex: amount: 250000000 currency: USD what_it_covers: refinery project (release states all amounts in US dollars unless otherwise stated) date: "2024-08-19" url: https://www.electrabmc.com/news-releases/news/electra-awarded-20-million-from-us-department-of-defense-under-the-defense-production-act quote: The $250 million refinery project is located north of Toronto, in Temiskaming Shores source_file: electra-dod-award.txt publisher: Electra Battery Materials Corporation backing: - body: U.S. Department of Defense (Defense Production Act Title III) instrument: grant stage_as_printed: awarded amount: 20000000 currency: USD date: "2024-08-19" url: https://www.electrabmc.com/news-releases/news/electra-awarded-20-million-from-us-department-of-defense-under-the-defense-production-act quote: it has been awarded $20 million by the U.S. Department of Defense source_file: electra-dod-award.txt publisher: Electra Battery Materials Corporation - id: vulcan-lionheart name: Zero Carbon Lithium (Phase One Lionheart Project) company: Vulcan Energie Ressourcen GmbH country_iso3: DEU place: Upper Rhine Valley materials: - lithium kind: mine_and_processing kind_as_printed: extraction project (Commission annex); integrated lithium and renewable energy project (company) status: construction status_fact: as_printed: Final Investment Decision in December 2025, when construction activities officially commenced date: "2026-05-27" url: https://www.v-er.eu/news-media/vulcan-reaches-financial-close-for-phase-one-lionheart-financing-package quote: The achievement follows the successful completion of the project's financing package and Final Investment Decision in December 2025, when construction activities officially commenced. source_file: eu-vulcan-financial-close.txt publisher: Vulcan Energy links: - publisher: European Investment Bank url: "https://www.eib.org/en/press/all/2025-486-vulcan-energy-secures-eur250-million-eib-financing-for-landmark-lithium-project-in-germany" backing: - body: European Commission instrument: strategic_project_status stage_as_printed: recognised as Strategic Project (Commission Decision C(2025) 1904, annex item 47) date: "2025-03-25" url: https://single-market-economy.ec.europa.eu/document/download/e9c90c91-7492-4047-bc51-d0c9d5e89a2f_en?filename=C_2025_1904_1_EN_annexe_acte_autonome_part1_v2.pdf quote: Zero Carbon Lithium is an ongoing extraction project in Germany. The project promoted by Vulcan Energie Ressourcen GmbH source_file: eu-ec-annex-2025-eu.txt publisher: European Commission - body: Raw Materials Fund (managed by KfW, under the Germany Fund) instrument: equity stage_as_printed: is investing up to amount: 150000000 currency: EUR date: "2026-09-09" url: https://www.kfw.de/About-KfW/Newsroom/Latest-News/Deutschlandfonds.html quote: Raw Materials Fund, under the umbrella of the Germany Fund, is investing up to EUR 150 million in the implementation of the ambitious Lionheart project source_file: eu-kfw-deutschlandfonds.txt publisher: KfW note: the KfW page prints 'News of 9 September 2026' above this item - id: talga-vittangi-anode name: Talga Natural Graphite ONE (Vittangi Anode Project) company: Talga AB country_iso3: SWE place: northern Sweden materials: - graphite kind: mine_and_processing kind_as_printed: extraction project (Commission annex); vertically integrated operation (company) status: planned status_fact: as_printed: FINANCIAL CLOSE DATE 31 January, 2028; ENTRY INTO OPERATION DATE 31 December, 2030 (Innovation Fund fiche for the anode refinery part) date: "2026-10-02" url: https://ec.europa.eu/assets/cinea/project_fiches/innovation_fund/101191036.pdf quote: FINANCIAL CLOSE DATE 31 January, 2028 ENTRY INTO OPERATION DATE 31 December, 2030 source_file: eu-cinea-talnodeone.txt publisher: European Climate, Infrastructure and Environment Executive Agency (CINEA) capex: amount: 560000000 currency: EUR what_it_covers: capital costs for the construction of the vertically integrated operation (excluding €39m contingency) date: "2024-04-15" url: https://talgagroup.eu-central-1.linodeobjects.com/app/uploads/2024/04/15091050/20240415FeedCompleted_ASX.pdf quote: capital costs for the construction of the vertically integrated operation are now estimated at €560 million (excluding €39m contingency) source_file: eu-talga-feed-2024.txt publisher: Talga Group Ltd links: - publisher: European Investment Bank url: "https://www.eib.org/en/projects/pipelines/all/20220643" backing: - body: European Commission instrument: strategic_project_status stage_as_printed: recognised as Strategic Project (Commission Decision C(2025) 1904, annex item 44) date: "2025-03-25" url: https://single-market-economy.ec.europa.eu/document/download/e9c90c91-7492-4047-bc51-d0c9d5e89a2f_en?filename=C_2025_1904_1_EN_annexe_acte_autonome_part1_v2.pdf quote: Talga Natural Graphite ONE is an ongoing extraction project in Sweden. The project promoted by Talga AB source_file: eu-ec-annex-2025-eu.txt publisher: European Commission - body: European Investment Bank instrument: loan stage_as_printed: "board has approved (EIB project page: Approved | 15/06/2023; amount 'not disclosed' there)" amount: 150000000 currency: EUR date: "2023-06-20" url: https://talgagroup.eu-central-1.linodeobjects.com/app/uploads/2023/06/20092357/20230620EIBApproval_ASX.pdf quote: board has approved €150 million senior debt funding source_file: eu-talga-eib-approval-2023.txt publisher: Talga Group Ltd - body: EU Innovation Fund instrument: grant stage_as_printed: AMOUNT OF INNOVATION FUND GRANT (project TalnodeONE, starting date 01 April, 2025) amount: 70000000 currency: EUR date: "2026-10-02" url: https://ec.europa.eu/assets/cinea/project_fiches/innovation_fund/101191036.pdf quote: AMOUNT OF INNOVATION FUND GRANT EUR 70,000,000 source_file: eu-cinea-talnodeone.txt publisher: European Climate, Infrastructure and Environment Executive Agency (CINEA) note: fiche 'Updated on 02 October 2026' - id: caremag-lacq name: CAREMAG company: Caremag SAS country_iso3: FRA place: Lacq, in the south of France materials: - rare-earths kind: processing kind_as_printed: processing project (Commission annex); rare earth recycling and refining industrial facility (company) status: construction status_fact: as_printed: ont posé la première pierre de l’usine Caremag date: "2025-03-31" url: https://www.tresor.economie.gouv.fr/Articles/2025/03/31/breves-economiques-japon-coree-du-sud-periode-du-1er-au-31-mars-2025 quote: les ministres Laurent Saint-Martin et Agnès Pannier-Runacher ont posé la première pierre de l’usine Caremag quote_en: the ministers Laurent Saint-Martin and Agnès Pannier-Runacher laid the foundation stone of the Caremag plant source_file: eu-tresor-breves-2025-03.txt publisher: Direction générale du Trésor capex: amount: 216000000 currency: EUR what_it_covers: financing secured to build the rare earth recycling and refining industrial facility in Lacq (printed as financing, not as a cost estimate) date: "2025-03-17" url: https://www.carester.fr/wp-content/uploads/2025/03/press-release-ENG-without-embargo.pdf quote: has secured €216 million to build its cutting-edge rare earth recycling and refining industrial facility in Lacq source_file: eu-carester-pr-2025.txt publisher: Carester backing: - body: European Commission instrument: strategic_project_status stage_as_printed: recognised as Strategic Project (Commission Decision C(2025) 1904, annex item 7) date: "2025-03-25" url: https://single-market-economy.ec.europa.eu/document/download/e9c90c91-7492-4047-bc51-d0c9d5e89a2f_en?filename=C_2025_1904_1_EN_annexe_acte_autonome_part1_v2.pdf quote: CAREMAG is an ongoing processing project in France. The project promoted by Caremag SAS source_file: eu-ec-annex-2025-eu.txt publisher: European Commission - body: French government instrument: other stage_as_printed: subsidies and repayable advances granted under the France Relance and France 2030 project calls, as well as a Green Industry tax credit amount: 106000000 currency: EUR date: "2025-03-17" url: https://www.carester.fr/wp-content/uploads/2025/03/press-release-ENG-without-embargo.pdf quote: this project is backed by €110 million from Japanese investors and €106 million from the French government source_file: eu-carester-pr-2025.txt publisher: Carester - id: emili-beauvoir name: EMILI company: IMERYS Ceramics France and IMERYS Lithium France country_iso3: FRA place: Allier materials: - lithium kind: mine_and_processing kind_as_printed: integrated extraction and processing project status: planned status_fact: as_printed: finalisation de l'étude de faisabilité définitive, jalon majeur prévu début 2027 date: "2026-02-11" url: https://presse.economie.gouv.fr/?p=170651 quote: vise à accompagner le projet EMILI dans la finalisation de l'étude de faisabilité définitive, jalon majeur prévu début 2027 quote_en: aims to support the EMILI project in completing the definitive feasibility study, a major milestone planned for early 2027 source_file: eu-minefi-emili-2026.txt publisher: Ministère de l'Économie, des Finances et de la Souveraineté industrielle, énergétique et numérique backing: - body: European Commission instrument: strategic_project_status stage_as_printed: recognised as Strategic Project (Commission Decision C(2025) 1904, annex item 12) date: "2025-03-25" url: https://single-market-economy.ec.europa.eu/document/download/e9c90c91-7492-4047-bc51-d0c9d5e89a2f_en?filename=C_2025_1904_1_EN_annexe_acte_autonome_part1_v2.pdf quote: EMILI is an ongoing integrated extraction and processing project in France. The project promoted by IMERYS Ceramics France and IMERYS Lithium France source_file: eu-ec-annex-2025-eu.txt publisher: European Commission - body: État français (via Banque des Territoires, France 2030) instrument: equity stage_as_printed: prise de participation de l'État au capital du projet (annoncée) amount: 50000000 currency: EUR date: "2026-02-11" url: https://presse.economie.gouv.fr/?p=170651 quote: L'investissement de l'État d'un montant de 50 millions d'euros quote_en: The State's investment of 50 million euros source_file: eu-minefi-emili-2026.txt publisher: Ministère de l'Économie, des Finances et de la Souveraineté industrielle, énergétique et numérique - body: EU Innovation Fund instrument: grant stage_as_printed: table column 'Innovation Fund grant (EUR million)'; project start 01/09/2026; covers the lithium hydroxide refinery plant amount: 116000000 currency: EUR date: "2026-11-01" url: https://ec.europa.eu/assets/cinea/country_factsheets/innovation_fund/INNOVFUND_France.pdf quote: 01/09/2026 Imerys Holding | Imerys 2,332,289 116.0 source_file: eu-cinea-if-france.txt publisher: European Climate, Infrastructure and Environment Executive Agency (CINEA) note: "factsheet prints 'State of play: November 2026' (no day)" amount_check: table cell in the column 'Innovation Fund grant (EUR million)' - id: cinovec-lithium name: Cínovec lithium project company: Geomet s.r.o. country_iso3: CZE place: Cínovec and Prunéřov, Ústí nad Labem Region materials: - lithium kind: mine_and_processing kind_as_printed: integrated extraction and processing project status: planned status_fact: as_printed: definitive feasibility study complete; shareholders will decide on the implementation and financing of the next stage date: "2025-12-19" url: https://www.cez.cz/en/media/press-releases/finalni-studie-proveditelnosti-je-hotova.-potvrdila-ze-projekt-tezby-a-zpracovani-lithia-je-realizovatelny.-do-konce-roku-bude-podana-eia-230527 quote: Geomet will now present the completed study to its shareholders, who will decide on the implementation and financing of the project’s next stage. source_file: eu-cez-cinovec-dfs.txt publisher: ČEZ capex: amount: 42000000000 currency: CZK what_it_covers: total investment of the lithium park (printed as 'more than 42 billion CZK') date: "2025-12-19" url: https://www.cez.cz/en/media/press-releases/finalni-studie-proveditelnosti-je-hotova.-potvrdila-ze-projekt-tezby-a-zpracovani-lithia-je-realizovatelny.-do-konce-roku-bude-podana-eia-230527 quote: The total investment of the lithium park is estimated at more than 42 billion CZK. source_file: eu-cez-cinovec-dfs.txt publisher: ČEZ backing: - body: European Commission instrument: strategic_project_status stage_as_printed: recognised as Strategic Project (Commission Decision C(2025) 1904, annex item 9) date: "2025-03-25" url: https://single-market-economy.ec.europa.eu/document/download/e9c90c91-7492-4047-bc51-d0c9d5e89a2f_en?filename=C_2025_1904_1_EN_annexe_acte_autonome_part1_v2.pdf quote: Cínovec lithium project is an ongoing integrated extraction and processing project in Czechia. The project promoted by Geomet s.r.o. source_file: eu-ec-annex-2025-eu.txt publisher: European Commission - body: Fair Transition Fund instrument: grant stage_as_printed: subsidy received this April amount: 800000000 currency: CZK date: "2025-12-19" url: https://www.cez.cz/en/media/press-releases/finalni-studie-proveditelnosti-je-hotova.-potvrdila-ze-projekt-tezby-a-zpracovani-lithia-je-realizovatelny.-do-konce-roku-bude-podana-eia-230527 quote: the CZK 800 million subsidy from the Fair Transition Fund that Geomet received this April source_file: eu-cez-cinovec-dfs.txt publisher: ČEZ - body: Czech government (Strategic Investments for a Climate Neutral Economy programme) instrument: grant stage_as_printed: approved a subsidy of up to; to be drawn between 2029 and 2031 amount: 350000000 currency: EUR date: "2025-12-19" url: https://www.cez.cz/en/media/press-releases/finalni-studie-proveditelnosti-je-hotova.-potvrdila-ze-projekt-tezby-a-zpracovani-lithia-je-realizovatelny.-do-konce-roku-bude-podana-eia-230527 quote: Czech government also approved a subsidy of up to 350 million euros (CZK 8.8 billion) from the Strategic Investments for a Climate Neutral Economy programme source_file: eu-cez-cinovec-dfs.txt publisher: ČEZ - id: barroso-lithium name: Barroso Lithium Project company: Savannah Lithium, Unipessoal, Lda. country_iso3: PRT materials: - lithium kind: mine kind_as_printed: extraction project status: planned status_fact: as_printed: Production targeted for end 2028 date: "2026-10-01" url: https://savannahresources.com/wp-content/uploads/2026/10/Savannah_IMCPresentation_Oct2026.pdf quote: Production targeted for end 2028. source_file: eu-savannah-pres-2026-10.txt publisher: Savannah Resources Plc note: presentation prints only 'OCTOBER 2026' capex: amount: 418000000 currency: USD what_it_covers: Capex total including pre-strip & contingency (Phase 1 DFS, July 2026); US$323m net of the State Grant date: "2026-10-01" url: https://savannahresources.com/wp-content/uploads/2026/10/Savannah_IMCPresentation_Oct2026.pdf quote: "Capex: Total of US$418m including pre-strip & contingency US$323m required net of US$95m contribution from State Grant" source_file: eu-savannah-pres-2026-10.txt publisher: Savannah Resources Plc note: presentation prints only 'OCTOBER 2026' backing: - body: European Commission instrument: strategic_project_status stage_as_printed: recognised as Strategic Project (Commission Decision C(2025) 1904, annex item 5) date: "2025-03-25" url: https://single-market-economy.ec.europa.eu/document/download/e9c90c91-7492-4047-bc51-d0c9d5e89a2f_en?filename=C_2025_1904_1_EN_annexe_acte_autonome_part1_v2.pdf quote: Barroso Lithium Project is an ongoing extraction project in Portugal. The project promoted by Savannah Lithium, Unipessoal, Lda. source_file: eu-ec-annex-2025-eu.txt publisher: European Commission - body: Portuguese State instrument: grant stage_as_printed: Awarded a non-reimbursable grant of up to amount: 110000000 currency: EUR date: "2026-04-15" url: https://savannahresources.com/wp-content/uploads/2026/04/Financial-Results-for-the-Year-Ended-31-Dec-2025.pdf quote: Awarded a non-reimbursable grant of up to EUR110m by the Portuguese State source_file: eu-savannah-fy2025.txt publisher: Savannah Resources Plc - body: German Government instrument: loan_guarantee stage_as_printed: eligible for a loan guarantee amount: 270000000 currency: USD date: "2026-04-15" url: https://savannahresources.com/wp-content/uploads/2026/04/Financial-Results-for-the-Year-Ended-31-Dec-2025.pdf quote: eligible for a loan guarantee from the German Government for up to USD270m source_file: eu-savannah-fy2025.txt publisher: Savannah Resources Plc - id: guben-lithium-converter name: Lithium Hydroxide Converter Guben company: Rock Tech Guben GmbH country_iso3: DEU place: Guben, Brandenburg materials: - lithium kind: processing kind_as_printed: processing project status: planned status_fact: as_printed: fully permitted; CapEx estimate updated date: "2025-10-23" url: https://rocktechlithium.com/wp-content/uploads/2025/10/Rock-Tech-News-Release-re-CapEx-Update-MoU-SCT-Arcore-Oct-22-2025.pdf quote: another significant milestone in the development of the fully permitted Guben Lithium Converter on the German-Polish border source_file: eu-rocktech-capex-2025-10.txt publisher: Rock Tech Lithium Inc. capex: amount: 680000000 currency: EUR what_it_covers: CapEx for commissioning the facility (management estimate) date: "2025-10-23" url: https://rocktechlithium.com/wp-content/uploads/2025/10/Rock-Tech-News-Release-re-CapEx-Update-MoU-SCT-Arcore-Oct-22-2025.pdf quote: management now estimates the CapEx for commissioning the facility at approximately €680 million, compared to the prior estimate of €730 million source_file: eu-rocktech-capex-2025-10.txt publisher: Rock Tech Lithium Inc. backing: - body: European Commission instrument: strategic_project_status stage_as_printed: recognised as Strategic Project (Commission Decision C(2025) 1904, annex item 24) date: "2025-03-25" url: https://single-market-economy.ec.europa.eu/document/download/e9c90c91-7492-4047-bc51-d0c9d5e89a2f_en?filename=C_2025_1904_1_EN_annexe_acte_autonome_part1_v2.pdf quote: Lithium Hydroxide Converter Guben is an ongoing processing project in Germany. The project promoted by Rock Tech Guben GmbH source_file: eu-ec-annex-2025-eu.txt publisher: European Commission - body: Brandenburg’s Ministry for Economic Affairs, Labour and Energy instrument: grant stage_as_printed: has issued an LOI committing up to amount: 90000000 currency: EUR date: "2024-06-27" url: https://rocktechlithium.com/en/rock-tech-to-receive-up-to-100-million-eur-in-direct-grants-for-its-german-lithium-refinery-funding-to-be-provided-by-the-state-of-brandenburg-and-the-german-railway-authority-further-applications-f/ quote: Brandenburg’s Ministry for Economic Affairs, Labour and Energy has issued an LOI committing up to 90 million EUR in grants source_file: eu-rocktech-grants.txt publisher: Rock Tech Lithium Inc. - body: German Railway Authority instrument: grant stage_as_printed: application for federal funding has been confirmed amount: 10000000 currency: EUR date: "2024-12-31" url: https://rocktechlithium.com/wp-content/uploads/2025/05/20241231_Rock-Tech-MDA-Q4-2024-FINAL-for-SEDAR.pdf quote: application for federal funding from the German Railway Authority has been confirmed and will provide a contribution of another 10 million Euros in grants source_file: eu-rocktech-mda-q4-2024.txt publisher: Rock Tech Lithium Inc. note: period end of the 2024 MD&A that prints this later: - date: "2024-12-31" url: https://rocktechlithium.com/wp-content/uploads/2025/05/20241231_Rock-Tech-MDA-Q4-2024-FINAL-for-SEDAR.pdf quote: The LOI expired on December 31, 2024. source_file: eu-rocktech-mda-q4-2024.txt publisher: Rock Tech Lithium Inc. what: "Brandenburg’s Ministry for Economic Affairs, Labour and Energy: The LOI expired on December 31, 2024." note: period end of the 2024 MD&A that prints this - id: tungsten-west-hemerdon name: Tungsten West (Hemerdon tungsten and tin mine) company: Tungsten West PLC country_iso3: GBR place: Devon materials: - tungsten kind: mine kind_as_printed: extraction project status: construction status_fact: as_printed: Construction is underway date: "2026-11-13" url: https://www.tungstenwest.com/project/hemerdon-mine quote: The permits are in place. Construction is underway. source_file: eu-tungstenwest-hemerdon.txt publisher: Tungsten West note: page is undated; date is the day it was fetched backing: - body: European Commission instrument: strategic_project_status stage_as_printed: recognised as Strategic Project in a third country (Commission Decision C(2025) 3491, annex item 12) date: "2025-06-04" url: https://single-market-economy.ec.europa.eu/document/download/60c576a5-435e-43e6-83de-c81f3652259b_en?filename=C_2025_3491_1_EN_annexe_acte_autonome_part1_v3.pdf quote: Tungsten West is an ongoing extraction project in the United Kingdom. The project promoted by Tungsten West PLC source_file: eu-ec-annex-2025-noneu.txt publisher: European Commission - body: National Wealth Fund (United Kingdom) instrument: equity stage_as_printed: has announced an investment amount: 36000000 currency: GBP date: "2026-08-25" url: https://www.nationalwealthfund.org.uk/news-and-publications/news/national-wealth-fund-backs-tungsten-west-to-unlock-critical-uk-tungsten-supply/ quote: The financing consists of a £36 million equity investment alongside up to £35 million of lending source_file: eu-nwf-tungsten-west-2026.txt publisher: National Wealth Fund - body: National Wealth Fund (United Kingdom) instrument: loan stage_as_printed: has announced an investment (up to £35 million of lending) amount: 35000000 currency: GBP date: "2026-08-25" url: https://www.nationalwealthfund.org.uk/news-and-publications/news/national-wealth-fund-backs-tungsten-west-to-unlock-critical-uk-tungsten-supply/ quote: The financing consists of a £36 million equity investment alongside up to £35 million of lending source_file: eu-nwf-tungsten-west-2026.txt publisher: National Wealth Fund